How do I change the start and/or end dates of my project?

Change the start and/or end dates of my projects.

✅ Your project is already created, and you are a member of the project.

🔓 Required Permissions

Team: Create projects

Project: Update projects

Reading time 1min
Setup length 1min
Steps 2

 

You want to modify the start and end dates of your project after creating the schedule, here is how to do it in 2 steps:

1) To start, go to the project in the Settings > Details tab and enter a new start and/or end date.

Then click save.

Finally, in Planning > Project planning, if the planning has not been updated, click on Actions > Reset planning dates

You will see that your phases have been distributed based on their fee shares and their new start and end dates.

Done! 🎉