How to transfer an employee's time recovery to another project ?

Time was recorded on the wrong project? Learn how to transfer logged hours from one project to another.

Updated over 2 weeks ago

🔓 Permissions required
Team: Super Admin
Project: Super Admin

Reading time

1 min

Setup length

1 min

Steps

1

It's possible and can be done in just a few steps:

  • Export times from old project

💡 Step-by-step tutorial: Click here

  • Delete project timesheets

screen delete project timesheets

  • Re-import the times into the correct project

💡 Here's how to import times on a project: Click here

Note: You can always manage the balance of recoveries by clicking on your name > settings > time on the left > users > recovery tab.

You can also manage the balance from the Collaborators menu on the left > collaborators tab > click on the profile of the relevant collaborator > time tab.